Oxford Council had various problems with their existing tank. The design left no clearance from the ceiling so no water treatment company had ever managed to get inside it to safely clean it.
There was 20 years of sediment build-up in the tank and the water samples always failed. Subsequently, the site had to have a very expensive water treatment programme in place involving dosing systems and constant monitoring.
The tank was also a one compartment tank, meaning that even if maintenance was possible it would have to be done out of hours because it would have to be drained down fully.
After a full survey, our team decided that a full GRP water tank replacement was the best option. Our experienced engineers designed a new GRP water tank for our client; the new tank had dual pipework and two compartments which would allow for more convenient cleaning and maintenance.
We also included internal and external ladders to allow for safer maintenance. Clarion Water managed the GRP water tank replacement project from start to finish and completed the project successfully. A description of the project can be found below:
If you require a GRP water tank replacement, or if you are having issues with your water tank and you need a professional solution, get in touch with Clarion Water today.